OpenPlant Project Administrator Help

Setup a Report to Link with PlantSight

Have a WorkSet associated with a Connected Project and provisioned to a PlantSight imodel.
  1. Click the Tools tab and open the Report Designer.
  2. When the reports are loaded, right click on a report and select Edit from the context menu.
  3. In the Edit Report dialog, check the PlantSight option from the Applications group
  4. Click OK to close the dialog.
  5. Click the Save option in the Report Designer to save the change. The next time you open the Consistency Manager in OpenPlant Modeler the report will appear under the Project Reports list: